Action |
Results of Successful Performance |
Initiating
|
1. Demonstrate project need and feasibility.
|
| |
A document confirming that there is a need for the project deliverables and describing, in broad terms: the deliverables, means of creating the deliverables, costs of creating and implementing the deliverables, benefits to be obtained by implementing the deliverables.
|
|
2. Obtain project authorization.
|
| |
A "go/no go" decision is made by the sponsor.
|
| |
A project manager is assigned.
|
| |
A "project charter" is created which:
 |
Formally recognizes the project
|
 |
Is issued by a manager external to the project and at a high enough organizational level so that he or she can meet project needs
|
 |
Authorizes the project manager to apply resources to project activities
|
|
|
3. Obtain authorization for the phase.
|
| |
A "go/no go" decision is made by the sponsor which authorizes the project manager to apply organizational resources to the activities of a particular phase
|
| |
Written approval of the phase is created which
| |
Formally recognizes the existence of the phase
|
| |
Is issued by a manager external to the project and at a high enough organizational level so that he or she can meet project needs
|
|
|
Planning
|
4. Describe project scope.
|
| |
Statement of project scope
|
| |
Scope management plan
|
| |
Work breakdown structure
|
|
5. Define and sequence project activities.
|
| |
An activity list (list of all activities that will be performed on the project)
|
| |
Updates to the work breakdown structure (WBS)
|
| |
A project network diagram
|
|
6. Estimate durations for activities and resources required.
|
| |
Estimate of durations (time required) for each activity and assumptions related to each estimate
|
| |
Statement of resource requirements
|
| |
Updates to activity list
|
|
7. Develop a project schedule.
|
| |
Project schedule in the form of Gantt charts, network diagrams, milestone charts, or text tables
|
| |
Supporting details, such as resource usage over time, cash flow projections, order/delivery schedules, etc.
|
|
8. Estimate costs.
|
| |
Cost estimates for completing each activity
|
| |
Supporting detail, including assumptions and constraints
|
| |
Cost management plan describing how cost variances will be handled
|
|
9. Build a budget and spending plan.
|
| |
A cost baseline or time-phased budget for measuring/monitoring costs
|
| |
A spending plan, telling how much will be spent on what resources at what time
|
|
10. Create a formal quality plan. (optional)
|
| |
Quality management plan, including operational definitions
|
| |
Quality verification checklists
|
|
11. Create a formal project communications plan. (optional)
|
| |
A communication management plan, including:
| |
Collection structure
|
| |
Distribution structure
|
| |
Description of information to be disseminated
|
| |
Schedules listing when information will be produced
|
| |
A method for updating the communications plan
|
|
|
12. Organize and acquire staff.
|
| |
Role and responsibility assignments
|
| |
Staffing plan
|
| |
Organizational chart with detail as appropriate
|
| |
Project staff
|
| |
Project team directory
|
|
13. Identify risks and plan to respond. (optional)
|
| |
A document describing potential risks, including their sources, symptoms, and ways to address them
|
|
14. Plan for and acquire outside resources. (optional)
|
| |
Procurement management plan describing how contractors will be obtained
|
| |
Statement of work (SOW) or statement of requirements (SOR) describing the item (product or service) to be procured
|
| |
Bid documents, such as RFP (request for proposal), IFB (invitation for bid),etc.
|
| |
Evaluation criteria -- means of scoring contractor's proposals
|
| |
Contract with one or more suppliers of goods or services
|
|
15. Organize the project plan.
|
| |
A comprehensive project plan that pulls together all the outputs of the preceding project planning activities
|
|
16. Close out the project planning phase.
|
| |
A project plan that has been approved, in writing, by the sponsor A "green light" or okay to begin work on the project
|
|
17. Revisit the project plan and replan if needed.
|
| |
Confidence that the detailed plans to execute a particular phase are still accurate and will effectively achieve results as planned.
|
|
Executing
|
18. Execute project activities.
|
| |
Work results (deliverables) are created.
|
| |
Change requests (i.e., based on expanded or contracted project) are identified.
|
| |
Periodic progress reports are created.
|
| |
Team performance is assessed, guided, and improved if needed.
|
| |
Bids/proposals for deliverables are solicited, contractors (suppliers) are chosen, and contracts are established.
|
| |
Contracts are administered to achieve desired work results.
|
|
Controlling
|
19. Control project activities.
|
| |
Decision to accept inspected deliverables
|
| |
Corrective actions such as rework of deliverables, adjustments to work process, etc.
|
| |
Updates to project plan and scope
|
| |
List of lessons learned
|
| |
Improved quality
|
| |
Completed evaluation checklists (if applicable)
|
|
Closing
|
20. Close out project activities.
|
| |
Formal acceptance, documented in writing, that the sponsor has accepted the product of this phase or activity.
|
| |
Formal acceptance of contractor work products and updates to the contractor's files.
|
| |
Updated project records prepared for archiving.
|
| |
A plan for follow-up and/or hand-off of work products |
|